Gemini Titan, LLC Product Self-Certification under 17 C.F.R. § 40.2(a) for “Will the BLS CPI-U year-over-year change for November 2026 be above 3.7%?” Event Contract.
Gemini Titan, LLC · received by the CFTC 29 October 2026 · the filing (PDF)
Warrant Check read 6 operative provisions in this filing. Across them, 23 of 36 checks are present, 1 partial and 10 absent. 3 provisions have every check present. 1 statement the exchange makes to the CFTC about the filing itself (such as that it complies with the Act) is not contract terms and is left out.
23 present1 partial10 absent2 not assessedThe payout rule here is “Primary settlement determination”: the rule that says what makes the contract pay Yes or No. The other 5 rules are fallback rules: what happens if the event is cancelled or delayed, the data goes missing, or the result is challenged.
| Topic the staff letters raise | Payout rule | Fallback rules |
|---|---|---|
| Settlement source identified | Addressed | 3 of 5 addressed |
| Settlement method described | Addressed | 2 of 5 addressed |
| Covers every case it applies to | Addressed | 3 of 5 addressed |
| Timing set | Addressed | 3 of 5 addressed |
| Terms in the public filing | In the filing | 3 of 5 in the filing |
What the wording addresses
- Primary settlement determination — every check present.
“whether the Measurement Value is above the Threshold” - Fallback to BLS source: Independent Verification, Defined Benchmark, Conclusive Link, Comprehensive Coverage, Relevant Timeline.
“the Source Agency has not reported the figure” - One-hour correction window — every check present.
“corrects the Measurement Value it reported as of” - Release postponement/rescheduling — every check present.
“If BLS postpones or reschedules the Official Release”
What the wording leaves open
- Fallback to BLS source “the Source Agency has not reported the figure”
- Suitable Method — Partial: Determining whether Mecone 'continues to display a value that has not been re-anchored' requires some interpretive judgment, not a purely mechanical check.
- No-release / 30-day discretionary resolution “does not issue the Official Release within thirty”
- Independent Verification — Absent: Resolution rests on the Exchange's own 'sole discretion' under an unreproduced internal rule, not any named third-party evidence.
- Suitable Method — Absent: Sole discretion is not a checkable procedure and cannot establish any specific numeric claim; the trigger condition (non-publication) is checkable but the consequence itself is not evidence-based.
- Defined Benchmark — Absent: No standard for 'last fair price' is stated in the supplied text; Rule 7.2 is referenced but not provided.
- Comprehensive Coverage — Absent: No defined population or data source for determining 'last fair price'; scope of the discretionary determination is unbounded in the text.
- Relevant Timeline — Absent: No temporal scope is defined for how the 'last fair price' is derived once discretion is invoked.
- Relies on material referred to but not in the public filing.
- Market Outcome Review / discretionary payout “the Exchange has the right to determine payouts”
- Independent Verification — Absent: Determination rests on the Exchange's own discretionary process under an unreproduced rule, not named third-party evidence.
- Suitable Method — Absent: A discretionary 'right to determine payouts' is not a checkable procedure capable of establishing a specific Expiration Value.
- Defined Benchmark — Absent: No threshold or methodology is given for how payouts are determined; Rule 7.1 is referenced but not supplied.
- Comprehensive Coverage — Absent: No defined population or data set for the Exchange's determination is stated in the text.
- Relevant Timeline — Absent: No time window for the review/determination process is specified in the supplied text.
- Relies on material referred to but not in the public filing.
Every provision read
Primary settlement determination
“whether the Measurement Value is above the Threshold”
Determination: The BLS CPI-U year-over-year figure for November 2026, as reported by Mecone, is above 3.7% · Consequence: Contract's Expiration Value is set to Yes or No, determining payout
Fallback to BLS source
“the Source Agency has not reported the figure”
Determination: Mecone has not reported the BLS figure by the Measurement Time · Consequence: Measurement Value is instead taken from the BLS Official Release (Fallback Source)
One-hour correction window
“corrects the Measurement Value it reported as of”
Determination: Mecone issues a correction to its reported value within one hour after the Measurement Time · Consequence: The corrected value, rather than the original, is used for settlement
No-release / 30-day discretionary resolution
“does not issue the Official Release within thirty”
Determination: BLS fails to publish the required 12-month CPI-U change within 30 days of the scheduled Measurement Date · Consequence: Contract resolves to 'the last fair price' as determined in the Exchange's sole discretion under Rule 7.2
Release postponement/rescheduling
“If BLS postpones or reschedules the Official Release”
Determination: BLS has postponed or rescheduled the Official Release to a new date/time · Consequence: Contract remains open and key dates/times (Measurement, Expiration, Last Trading) are substituted accordingly
Market Outcome Review / discretionary payout
“the Exchange has the right to determine payouts”
Determination: Neither the Source Agency nor the Fallback Source reports the Measurement Value, and an Expiration Value cannot otherwise be determined · Consequence: Exchange determines payouts under Rule 7.1 in an undefined review process
Read 3 November 2026 with Warrant Check (instrument 1.0). Labels: Present, Partial, Absent describe whether each check is found in the wording as written. Not assessed: Conclusive Link cannot be judged where no Defined Benchmark is named; that follows from the missing benchmark and is not a separate gap.
Drafting a certification?
Have the draft read through the same lens before it is filed: privately, with nothing published. You get what the wording addresses and what it leaves open, term by term, including the fallback rules for cancellation, delay, missing data and challenged results, where gaps most often sit.